Systematization and asphalting of Burgu road
Project overview
Within the framework of the project for the systematization and asphalting of the Burgu road village Vaqarr, a series of necessary works have been carried out as follows:
1. Demolition works
- Demolition of fences, constructions, concrete.
2. Road works
- Excavation with machines.
- First layer with gravel t=20 cm.
- Second layer with gravel t=15 cm.
- Layer with stabilizer t=10 cm.
- Binder layer t=6cm.
- Asphaltoconcrete layer with machines with t=4 cm.
- Concrete M-200 for placing curbs on both sides of the road.
- Placement of borders 20x35 cm.
- Placement of borders 15x35 cm.
- Road marking with two-component paint with a width of 15 cm.
3. White water sewers
- Digging the channel up to h=1.1m with machinery.
- Installation of ribbed pipe with a diameter of 400 mm.
- Sand for filling pipes with a thickness of 10 cm.
- Rainwater wells 40x60 h=1 with cast iron cover.
4. Pavement works
- Laying the gravel layer of 15 cm.
- Placement of three ribbed pipes with a diameter of 75 mm for electricity, telephone, etc.
- Construction of control wells 1x1x1.5, electro-telephone.
- Steel for retaining walls.
- Concrete t=11-20 cm C 16/20, h=4 m for retaining walls.
- Concrete C 16/20 for the pavement layer with a thickness of t=10 cm.
- Pavement with 6 cm concrete, with tiles.
5. Electrical works for street lighting
- Bases C 16/20 prefabricated for metal posts.
- Supply and placement of metal poles for lighting h=7 m, d=160 mm.
- Xingato electrode 50x 3 mm x 1.5 m.
- Lighting cable 4x25 mm.
- Plastic well 40x40x40 cm.
- Smart lamp with 250 W, 230 V lamp.
- Control panel.
- Terminal block 3 P + fuse 16 A + cover.