Systematization and asphalting of Burgu road

Facts and Figures

Project overview

Within the framework of the project for the systematization and asphalting of the Burgu road village Vaqarr, a series of necessary works have been carried out as follows:

1. Demolition works

  • Demolition of fences, constructions, concrete.

2. Road works

  • Excavation with machines.
  • First layer with gravel t=20 cm.
  • Second layer with gravel t=15 cm.
  • Layer with stabilizer t=10 cm.
  • Binder layer t=6cm.
  • Asphaltoconcrete layer with machines with t=4 cm.
  • Concrete M-200 for placing curbs on both sides of the road.
  • Placement of borders 20x35 cm.
  • Placement of borders 15x35 cm.
  • Road marking with two-component paint with a width of 15 cm.

3. White water sewers

  • Digging the channel up to h=1.1m with machinery.
  • Installation of ribbed pipe with a diameter of 400 mm.
  • Sand for filling pipes with a thickness of 10 cm.
  • Rainwater wells 40x60 h=1 with cast iron cover.

4. Pavement works

  • Laying the gravel layer of 15 cm.
  • Placement of three ribbed pipes with a diameter of 75 mm for electricity, telephone, etc.
  • Construction of control wells 1x1x1.5, electro-telephone.
  • Steel for retaining walls.
  • Concrete t=11-20 cm C 16/20, h=4 m for retaining walls.
  • Concrete C 16/20 for the pavement layer with a thickness of t=10 cm.
  • Pavement with 6 cm concrete, with tiles.

5. Electrical works for street lighting

  • Bases C 16/20 prefabricated for metal posts.
  • Supply and placement of metal poles for lighting h=7 m, d=160 mm.
  • Xingato electrode 50x 3 mm x 1.5 m.
  • Lighting cable 4x25 mm.
  • Plastic well 40x40x40 cm.
  • Smart lamp with 250 W, 230 V lamp.
  • Control panel.
  • Terminal block 3 P + fuse 16 A + cover.