Reconstruction of the building 26 in the Student City

Facts and Figures

Project overview

Within the project for the reconstruction of Building no. 26, a series of necessary works have been carried out to improve its structure and functionality. Works include:

1. Demolition works:

  • Demolition of majolica tiles, to prepare the surfaces for the new materials.
  • Demolition of internal and external plastering, creating a clean base for further reconstruction.
  • Demolition of balcony railings.
  • Demolition of the base of the stairs, so that it can be replaced with a more durable material.
  • Removal of existing doors and windows.
  • Demolition of paving slabs, to reshape spaces according to new standards.
  • Removal of the existing paint on the facades, to enable a new and modern application.
  • Damage to xingato pipes.

2. Plastering works:

  • Covering the walls with majolica tiles.
  • Plaster dressing.
  • Plastering of walls and ceilings.
  • External plastering to protect the structure from external factors.
  • Repair of window sills.
  • Patination of the walls.
  • Painting with oil paint for wall surfaces.
  • Painting with lime mortar.
  • Painting with oil paint for metal surfaces, guaranteeing protection from corrosion.
  • Painting with plastic paint for internal surfaces.
  • Painting with hydro mats, for a smooth and moisture-resistant surface.

3. Layer works:

  •  Paving with stoneware tiles in the corridor.
  • Laying with pavement tiles.
  • 1:2 mortar layer, providing a solid base.
  • Concrete layer for sidewalks with a thickness of 10 cm.
  • Supply and installation of marble window sills.
  • Supply and placement of the wooden strip in the corridors.
  • Supply and installation of the ceramic plinth.
  • Marble staircase plinths.
  • Supply and installation of parapets for balconies and stairs.

4. Door and window works:

  • Supply and installation of duralumin windows.
  • Supply and installation of duralumin flags.
  • Supply and installation of doors for rooms.

5. Terrace works:

  • Demolition of the existing waterproofing, to enable a new application.
  • Waterproofing with two layers of 4 mm bituminous membrane.
  • 1:2 mortar layer with a thickness of 3 cm.
  • Supply and installation of parapets.
  • Supply and installation of gutters.

6. Hydro sanitary works:

  • Supply and placement of various materials, including plastic pipe with different diameters (20, 25, 32, 160, 50, 40, 100 mm).
  • Elbows with different diameters (32, 20, 50 mm).
  • Reductions (32/25, 25/20, 100160, 10050, 50*32), toilet sleeves 25 mm, junto 20 mm, and rolling shutter with different diameters (32, 20 mm).
  • Supply and installation of facades with different diameters (25, 20, 50 mm).
  • Sink with column and group, lighting, toilet mirror with lighting.