Within the project for the reconstruction of garden no. 18, a series of necessary works have been carried out to improve its structure and functionality. Works include:
A - Construction works
A-1 Excavation and demolition works
A-2 Masonry works
A-3 Construction works
A-4 Terrace works
A-5 Refinishing and layering works
A-6 Window and door works
B- Hydro sanitary installations
B-1 Sanitary equipment
B-2 Water supply inside the building
B-3 Cold water supply outside the building
C- Sewerage works
C-1 Exhaust installations inside the building
C-2 Drainage installations outside the building (including rainwater)
D- Electrical works
D-1 Electrical equipment
D-2 Electrical installations:
- Power, lighting and signaling system
- Electrical panels
- Fire alarm system
- Signage and indexing code
E- Works for the heating system
E-1 Space heating
E-2 Technical room