Construction of internal roads of the CCBS area

Facts and Figures

Project overview

In the project for the construction of internal roads in the CCBS environment, numerous works have been carried out to ensure a functional and sustainable road infrastructure. Works include:

1- Road construction works and layers

Scarification of the existing layer: Scarification of the existing surface was carried out to prepare the ground for the new construction.
Gravel filling and compaction (20 cm): Gravel filling and compaction was carried out to create a strong and stable base.
Profiling with stabilizer: Stabilizer was applied to improve surface stability and prepare for future layers.

2- Layer works

Binder layer: A binder layer was placed to provide firm support for the asphalt layer.
Spraying with bituminous emulsion: After placing the binder layer, spraying with bituminous emulsion was carried out to guarantee the bond between the layers.

3- Asphalt concrete layer

Asphalt concrete layer: A reinforced asphalt concrete layer was laid by emulsion spraying, providing a stable and safe surface for traffic.

4- Curb and sewer works

Supply and placement of concrete curbs: The supply and placement of concrete curbs was carried out to limit and organize the spaces.
T/Normal excavation and side channels: Excavation of forced sections was carried out to create side channels for water drainage.
Supply and installation of PE pipes: The supply and installation of PE pipes with diameters of 315 mm and 630 mm for the sewage system was carried out.
Construction of rain wells: Rain wells were built with M-200 concrete and cast iron gutters for efficient surface water management.